Summary
Overview
Work History
Education
Skills
Accomplishments
Area Of Expertise
References
Timeline
Generic

Ishak Hadi Winarto

Project Manager
Batangas, Province Of Batangas,BTG

Summary

Professional Project Manager/ Commissioning manager, MBA graduated with Mechanical engineering background. Over 25 years outstanding experiences in leading multi-disciplinary teams of both thermal and gas turbine power plant projects. Expert in power generation project management and O&M management during commercial operation. Extensive experience working in EPC environment in Asia and Middle East, from bidding process, contract negotiation, engineering, construction, commissioning, project hand-over including warranty period, for large project up to1400 MW. Wide experience with different equipment manufacturers of coal fired/biomass boiler, steam turbine, HRSG and gas turbine, seawater steam-desalination/ RO project.

Overview

26
26
years of professional experience

Work History

Power Plant Consultant

DMCI Palawan and Masbate coal power plant
2023.08 - Current
  • Collaborated with cross-functional teams to successfully deliver comprehensive solutions for clients.
  • Provided ongoing support to clients post-implementation, ensuring long-term success of implemented solutions.

Project Manager

DMCI, 1x15MW CFB and Biomass Project
2021.04 - 2023.07
  • Successfully supervised and managed EPC contractor during project execution in order to deliver the project within 20 months, in scope and quality according to the contract.
  • Achieved the implementation of all Safety procedures, Inspection & Quality control procedures, construction and commissioning procedures.
  • Successfully monitor and control the project schedule, also to ensure Owner’s scope are delivered on-time (materials, equipment, O&M manpower, permits).
  • Report the project progress, cost implication and critical issues/risks to Owner’s Project Director.

Team Leader

DMCI Technical Group for Bidding 2x350MW Project
2020.10 - 2021.03
  • Lead a multi-discipline technical team to create the Term of Reference (TOR)/ Technical specification for the bidders.
  • Review bidder’s track record and performance in the Philippines and at the country of origin, prior to the bidder’s invitation.
  • Manage technical clarification process with the bidders in term of design technology, manufacturer preferences, quality standards, materials selection for critical equipment.
  • Review and evaluate bidder’s proposal and provide recommendation to the Owner

Project Manager

DMCI, Retrofitting 2x300 MW Power Plant
2019.10 - 2020.05
  • Successfully executed retrofitting project in six months, with main activities: replacement of boiler water wall, economizer and LTSH, replacement of four rotary Air preheater basket, replacement LP turbine and Hydrogen cooled generator, replacement of condenser tubes modules, conversion of turbine driven to motor driven boiler feed pump.
  • Overcome the challenging condition in which the last two months was lock-down under Covid-19 pandemic and access restriction for foreigner.

Commissioning advisor

JGC Philippines, 2x118 MW CFB Project
2018.04 - 2019.09

Warranty Manager

DMCI, 2x150 MW CFB Project
2017.10 - 2018.03
  • Reduced warranty costs by implementing effective quality control measures and proactive maintenance strategies.

Commissioning Manager

DMCI, 2x150MW CFB Project
2017.02 - 2017.09

Warranty Manager

DMCI, 2x135 MW CFB Project
2016.05 - 2017.01

Commissioning Manager

DMCI, 2x135MW CFB Project
2014.07 - 2016.04
  • Successfully managed overall process of commissioning in term of schedule, quality, cost, resources/ logistic.
  • Conducted Site Commissioning Committee roles to achieve proper coordination with the owner, National grid authority, O&M Company and certification authority.
  • Achieved the implementation of safety procedure and accident prevention though out projects duration.

Commissioning Manager

Alghanim International, 2x200MW Combined Cycle
2012.10 - 2014.06

Commissioning Manager

ZPT, 2x315 MW Coal Fired Project
2009.04 - 2012.09

Deputy Commissioning Manager

Siemens, 1000 MW Combined Cycle and Desalination
2008.06 - 2008.12

Operation Manager

Siemens, 1000MW Combined Cycle and Desalination
2008.03 - 2008.05

Shift Charge Engineer

Siemens, 1000MW Combined Cycle and Desalination
2007.08 - 2008.02

Shift Charge Engineer

Siemens, 750MW Combined Cycle Project
2007.03 - 2007.07

Boiler Field Service/Start Up Engineer

Babcock & Wilcox, 2x710MW Project
2005.12 - 2006.12

Assistant Shift Manager

Powergen/ YTL Jawa Timur, 2x610MW Private Power
2001.03 - 2005.11

Control Room Engineer

Powergen/ YTL Jawa Timur, 2x610 MW Private Power
2000.04 - 2001.02

Unit Controller

Powergen/ YTL Jawa Timur, 2x610MW Private Power
1999.04 - 2000.03

Graduate Training

Powergen/ YTL Jawa Timur, 2x610MW Private Power
1998.02 - 1999.03

Education

MBA - Business Administration

Lyceum of The Philippines University
Batangas, Philippines
2001.04 -

Bachelor of Science - Mechanical Engineering

Brawijaya University of Malang
Malang, East Java
2001.04 -

Certified Project Management Professional (PMP) -

Project Management Institute (PMI)

Skills

Project management

Team Leadership & Development

Quality Assurance

Commissioning

Gas Turbine

Steam Turbine

Boiler/HRSG

Biomass

Water Desalination

Accomplishments

  • Achieved the target schedule for Life Extension project 2x300 MW coal fired power plant 2019-2020, with boiler sub-contractor from China (NEPC) in which starting on March 2020, Philippines was under enhanced community quarantine (lockdown).
  • Successfully executed 300 MW Boiler pressure parts retrofitting with 100% welding joints NDT, i.e replacement of water wall, Economizer, Low temperature superheater coils, and managed to finish within 90 days as per target schedule.
  • Successfully coordinated the replacement activities of 300 MW hydrogen cooled generator and replacement of two condenser modules of 300 MW using 750 ton cranes as per target schedule and quality standard.
  • Early detection of IP coupling cracks of 150 MW steam turbine in March 2018, through constant monitoring of ADRE with assistant of vibration specialist. So, the major catastrophic damage was prevented.
  • Successfully lead technical discussion with Sulzer and turbine OEM, i.e. to arrange HIP rotor transportation to Sulzer Indonesia for rebuild the IP coupling, stress released, low speed balancing and sent back to Philippines via air-cargo, to investigate and determine the root cause of the crack, and subsequently implement the corrective action. Assist power plant owner for the claim of loss of generation/ business interruption and repair cost to the insurance.
  • Hired by Sulzer during commissioning stage of Vung Ang 600 MW steam turbine retrofitting project and successfully performed Cold start up.
  • Experiencing various cases of steam turbine vibration during commissioning, such as rubbing, resonance and bearing instability, and implement the correction. Having basic understanding of ADRE diagnostic system presentation such as polar, orbit, shaft centerline, spectrum, etc.
  • Successfully coordinated start up and commissioning of 3 x 270 MW Siemens Gas Turbine 94.3A (annular combustion chamber, dual fuel with Hydraulic Clearance Optimization) and HRSG (dual pressure horizontal steam drum with supplementary firing). Including Commissioning activities such as GT load rejection test, HRSG trip test, Steam turbine trip test form full load, Black start test, chemical cleaning, steam blow, load rejection test and performance test.
  • Having good experience as Startup engineer for 710 MW Boiler, Babcock &Wilcox – natural circulation, front & rear wall DRB-XCL burners, as well as 630 MW Boiler, ABB CE - sub critical forced water circulation, tangential firing with tilting nozzle.
  • Possessing and apply sound experience with Siemens Steam Turbine 630 MW and Hydrogen cooled generator with stator water cooled.
  • Appointed as the SAP (Senior Authorized Person) under Powergen Safety Rule, responsible to achieving safety from the system to allow maintenance team work safely (PTW system). Authorized to issue permit Confined space, Hot Work, ROMP, Testing on High Voltage, etc.
  • Sound working knowledge of control and protection system philosophy, tuning, DCS, PLC and redundancy system.
  • Familiar with the following DCS: Siemens Teleperm XP, ABB Advant system, Alstom Alspa and Toshiba Tosmap

Area Of Expertise

  • Project Management
  • Contract/Scope Management
  • Cost Management
  • Risk management
  • Design engineering
  • Construction/ Commissioning
  • Operation & Maintenance
  • Quality management
  • Plant Performance and Reliability
  • Control and Protection

References

  • Mr. Thorsten Heinz, Siemens Site Manager - Al Taweela NBE Project, thorsten.heinz@siemens.com
  • Mr. Fadi Haddad, Alghanim International Vice President – Azzour South CCGT2 Project, +965 99441138
  • Mr. Christopher R. Rodriguez, DMCI Business development, +63 9175395985
  • Mr. Joffrey B. Gacula, DMCI Construction Managing Director, +63 9088860762

Timeline

Power Plant Consultant

DMCI Palawan and Masbate coal power plant
2023.08 - Current

Project Manager

DMCI, 1x15MW CFB and Biomass Project
2021.04 - 2023.07

Team Leader

DMCI Technical Group for Bidding 2x350MW Project
2020.10 - 2021.03

Project Manager

DMCI, Retrofitting 2x300 MW Power Plant
2019.10 - 2020.05

Commissioning advisor

JGC Philippines, 2x118 MW CFB Project
2018.04 - 2019.09

Warranty Manager

DMCI, 2x150 MW CFB Project
2017.10 - 2018.03

Commissioning Manager

DMCI, 2x150MW CFB Project
2017.02 - 2017.09

Warranty Manager

DMCI, 2x135 MW CFB Project
2016.05 - 2017.01

Commissioning Manager

DMCI, 2x135MW CFB Project
2014.07 - 2016.04

Commissioning Manager

Alghanim International, 2x200MW Combined Cycle
2012.10 - 2014.06

Commissioning Manager

ZPT, 2x315 MW Coal Fired Project
2009.04 - 2012.09

Deputy Commissioning Manager

Siemens, 1000 MW Combined Cycle and Desalination
2008.06 - 2008.12

Operation Manager

Siemens, 1000MW Combined Cycle and Desalination
2008.03 - 2008.05

Shift Charge Engineer

Siemens, 1000MW Combined Cycle and Desalination
2007.08 - 2008.02

Shift Charge Engineer

Siemens, 750MW Combined Cycle Project
2007.03 - 2007.07

Boiler Field Service/Start Up Engineer

Babcock & Wilcox, 2x710MW Project
2005.12 - 2006.12

MBA - Business Administration

Lyceum of The Philippines University
2001.04 -

Bachelor of Science - Mechanical Engineering

Brawijaya University of Malang
2001.04 -

Assistant Shift Manager

Powergen/ YTL Jawa Timur, 2x610MW Private Power
2001.03 - 2005.11

Control Room Engineer

Powergen/ YTL Jawa Timur, 2x610 MW Private Power
2000.04 - 2001.02

Unit Controller

Powergen/ YTL Jawa Timur, 2x610MW Private Power
1999.04 - 2000.03

Graduate Training

Powergen/ YTL Jawa Timur, 2x610MW Private Power
1998.02 - 1999.03

Certified Project Management Professional (PMP) -

Project Management Institute (PMI)
Ishak Hadi WinartoProject Manager