Skilled in calibrating and maintaining all instrumentation devices for systems in Power Plant facilities. Proven to interpret schematics and diagrams to make accurate repairs and updates. Accomplished Technician skilled in troubleshooting, diagnostics and service on diverse instrumentation. Configures components for optimal performance. Talented repairer with organized and systematic approach to problem-solving. Dedicated Instrumentation Technician with more than five years of experience repairing instruments, machines and tools. Disciplined and hardworking team player with proven history of fast and detail-oriented work.
Has four years of technical experience in the field of system integration, including migration of old Allen Bradley PLC5 to ControlLogix, SLC or MicroLogix to CompactLogix, PanelView Standard to PanelView Plus, RSView32 Works to FactoryTalk View SE. design new control depends of the requirements of the client and conduct basic training from the project. Experienced on panel design and assembly specially on plc, remote i/o and mcc panels.
Preventive Maintenance
undefinedAfter internship, I was assigned on 2015 at U.S. Naval Support Facilities, Diego Garcia, B.I.O.T (British Indian Ocean Territory) project name Potable Water Plant Modernization under San Juan Construction as my previous company's general contractor for the project.
I am Registered Master Electrician PRC Lic No. 0067772 registered date November 3, 2022 I've also completed the Bosiet with EBS and H2S Awareness and STCW Basic Training, Seafarer's Record Book No. A0286888 and Seafarer's Identity Document No. 230161764 was issued last November 28, 2023
Basic Offshore Safety Induction and Emergency Training (Bosiet w/ EBS)
Project Name : R.O. Plant Sea Water Panel Relocation Project
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2022
Project Description
Existing PLC Panel is installed underground CRF System, and the panel and devices are in bad condition and maintenance and troubleshooting is not easy due to environment and noise.
New panel and devices are provided by contractors in part of RO Plant’s PLC Upgrade Phase 3. Decommissioned existing panel and cable tray and installed the new panel ground level of CRF system. Installed new cable trays and junction box for the 240 VAC supply and field devices and configured the new CompactLogix 5380 PLC with new IP assignments.
Project Name : R.O. Plant VDR5 Panel Relocation Project
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2022
Project Description
Existing PLC Panel is installed outside RO Plant’s pump room, and the panel and devices are in bad condition.
New panel and devices are provided by contractors in part of RO Plant’s PLC Upgrade Phase 2. Decommissioned existing panel and cable tray and installed the new panel inside the pump room. Installed new cable trays and junction box for the 240 VAC supply and field devices and configured the new CompactLogix 5380 PLC with new IP assignments.
Project Name : R.O. Plant DMF Solenoid Valves Relocation Project
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2022
Project Description
RO Plant’s DMF pneumatic actuators solenoid valves are exposed to sunlight, rain and dust because the DMF are has no roofing. The said exposure is the main cause of early deterioration of the solenoid valves that cause tripping and down time.
Installed the refurbished panel from Skids PLC and mounted all solenoid and isolation valves in the panel. Layout new 3/8” stainless tubing from actuator to DMF SV panel and layout new cables for solenoid valves and position feedback to PLC remote panel.
Project Name : Ash Plant Unit 1 and 2 additional SCADA
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2020
Project Description
Installation of new PC for both units. Clone of unit 1 and unit 2 SCADA to newly installed PC. Existing SCADA program is Wonderware 2014 R2.
Project Name : Electro-chlorination Plant Water Leak System
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2018
Project Description
Electrical layout and installation of water leak sensor. Minor edit for PLC program and SCADA program, alarm/fault status for water leak system. Existing PLC is Allen Bradley SLC 500 and for SCADA is Wonderware 2012 R2.
Project Name : Atlas Copco / Ingersoll Rand Compressor SCADA
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2018
Project Description
Revision of SCADA program on existing SCADA on unit 1 and additional SCADA for unit 2 for dual monitoring purpose. Existing SCDA program is Wonderware 2012 R2
Project Name : Waste Water Treatment Plant PLC and SCADA Upgrade
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2017
Project Description
Conversion of old PLC-5 primary and secondary chassis with a redundant system to new ControlLogix Programmable logic controller. Configuration of network for the new ControlLogix PLC to communication to SCADA. DH+ communication is upgraded to Ethernet with a ring topology method. Upgrade of old SCADA workstation to new SCADA workstation with Wonderware 2014 R2
Project Name : Conveyance Lift Station Project
Company : DM Consunji Inc.
Sucat, Paranaque City
Year : 2017
Project Description
Panel Layout and assembly. Installation and wiring of devices. On-site, installation of MCC Panes and Cage. Termination of pumps and float switches to PLC Input and Output modules.
Project Name : Desalination Plant PLC and SCADA Upgrade
Company : Quezon Power Philippines, Limited Co, QPL
Brgy. Cagsiay 1, Mauban, Quezon
Year : 2017
Project Description
Upgrade of old PLC-5 primary and secondary chassis redundant system and PLC-5 Remote I/Oto new ControlLogix Programmable Logic Controller. Upgrade of old SCADA RSView32 to new SCADA Factorytalk View Site Edition, and DH+ communication is also upgraded to Ethernet communication with a ring topology method.
Project Name : Demineralization Plant PLC and HMI Upgrade
Company : Quezon Power Philippines, Limited Co, QPL
Brgy. Cagsiay 1, Mauban, Quezon
Year : 2017
Project Description
Upgrade of old PLC-5 primary and secondary chassis redundant system and PLC-5 Remote I/Oto new ControlLogix Programmable Logic Controller. Uprade of old HMI PanelView to new HMI PanelView Plus 1000, and DH+ communication is also upgraded to Ethernet communication with a ring topology method.
Project Name : Ash Plant High Level PLC Conversion
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2016
Project Description
Panel design and assembly. Installation and wiring of devices. Conversion of old PLC-5 primary and secondary chassis with a redundant system and Unit 1 & 2 Remote I/O to new ControlLogix PLC. Dismantle of old PLC-5 PLC and wiring of field devices to new CLX PLC. Upgrade of old SCADA workstation to new SCADA workstation with Wonderware 2012 R2.
Project Name : Demineralization Plant PLC and SCADA Conversion
Company : Team Energy – Sual Power Station
Brgy. Pangascasan, Sual, Pangasinan
Year : 2016
Project Description
Conversion of old PLC-5 primary and secondary chassis with a redundant system to new ControlLogix Programmable logic controller. Configuration of network for the new ControlLogix PLC to communication to SCADA. DH+ communication is upgraded to Ethernet with a ring topology method. Upgrade of old SCADA workstation to new SCADA workstation with Wonderware 2012 R2.
Project Name : MCWD Surveillance and SCADA Project Phase II
Company : Mabalacat City Water District
Brgy. Mabiga, MacArthur Hi-Way, Mabalacat City, Pampanga
Year : 2016
Project Description
Configuration of devices wired to PLC analog and digital modules. PLC is linked to SCADA with a wireless communication. Monitoring and troubleshooting of transmitter devices.
Project Name : MCWD Surveillance and SCADA Project Phase I
Company : Mabalacat City Water District
Brgy. Mabiga, MacArthur Hi-Way, Mabalacat City, Pampanga
Year : 2015
Project Description
Enhancing of MCWD 30 Pump Stations. Monitoring and Control in SCADA and selection of Local or Remote for 30 Pump Stations. Panel design and assembly. Installation and wiring of devices. Wiring of field devices to PLC analog and digital modules. Upgrade of old Flowmeters to new Toscano T-500 and pressure transmitters to new FineTek EC1510-016G-3U-D-5.
Project Name : Jetty PLC Upgrade
Company : AES Philippines Masinloc Power Partners Co., Ltd.
Brgy. Bani, Masinloc, Zambales
Year : 2015
Project Description
Upgrade of old PLC-5 PLC to new ControlLogix PLC. Dismantle and Installation, wiring of field devices to new hardware, and configuration of old DH+ communication to ethernet communication using ring topology network.
Project Name : Potable Water Plant Modernization
Company : San Juan Construction Inc.
U.S. Naval Support Facilities, Diego Garcia, B.I.O.T
(British Indian Ocean Territory)
Year : 2015
Project Description
Panel assembly. Installation of devices and wiring to Remote I/O Panels. Termination of field devices to Point I/O modules. Remote I/O panels communication use Fiber Optics.
Project Name : Stacker-Reclaimer B PLC Upgrade
Company : AES Philippines Masinloc Power Partners Co., Ltd.
Brgy. Bani, Masinloc, Zambales
Year : 2015
Project Description
Upgrade of old PLC-5 primary and secondary chassis redundant system and PLC-5 Remote I/Oto new ControlLogix Programmable Logic Controller. Uprade of old HMI PanelView to new HMI PanelView Plus 1000, and DH+ communication is also upgraded to Ethernet communication with a ring topology method.
Project Name : Stacker-Reclaimer A PLC Upgrade
Company : AES Philippines Masinloc Power Partners Co., Ltd.
Brgy. Bani, Masinloc, Zambales
Year : 2015
Project Description
Upgrade of old PLC-5 primary and secondary chassis redundant system and PLC-5 Remote I/Oto new ControlLogix Programmable Logic Controller. Uprade of old HMI PanelView to new HMI PanelView Plus 1000, and DH+ communication is also upgraded to Ethernet communication with a ring topology method.
Project Name : IS Automation Migration Project
Company : Nestle Philippines Lipa Factory
Brgy. Bagong-Pook, Lipa, Batangas City
Year : 2014
Project Description
Migration of Demi, WWTP, Centac, Chiller, Air Handling Unit, Air Compressor and Dryer, Cooling Tower and Deep Well old SLC 500 PLC to new CompactLogix PLC and old PanelView to new PanelView Plus HMI and DH+ communication to ethernet communication using a ring topology method.
Project Name : Simatic S5 PLC to Simatic S7-300 Casepacker PLC Upgrade
Company : Pepsi Cola Products Philippines
Dumoy Toril, Davao City
Year : 2014
Project Description
Installation and wiring of devices. Conversion of old Siemens Simatic S5 PLC to new Siemens Simatic S7-300 PLC. Installation of Siemens Touch HMI. Wiring of field devices to new Simatic Siemens Digital Input and Output module and Analog Input and Output modules
Project Name : Simatic S5 PLC to Simatic S7-300 Uncaser PLC Upgrade
Company : Pepsi Cola Products Philippines
Dumoy Toril, Davao City
Year : 2014
Project Description
Installation and wiring of devices. Conversion of old Siemens Simatic S5 PLC to new Siemens Simatic S7-300 PLC. Installation of Siemens Touch HMI. Wiring of field devices to new Simatic Siemens Digital Input and Output module and Analog Input and Output modules.
Basic Offshore Safety Induction and Emergency Training (Bosiet w/ EBS)
Hydrogen Sulphide Awareness
STCW Basic Training
Registered Master Electrician [PRC Lic No.
Basic Operation of MIR 9000 Advance Training and Maintenance of MIR 9000
DCS Ovation 3.3.1 Training
Calibration for Process Instrumentation (CPI)
Beamex MC6, Multi-function Calibrator
Maintenance and System Training of Envea MIR 9000
Pneumatic and Hydraulics (P&H)
Networking Essentials TCP/IP Fundamentals and Subnetting
Mechatronics Servicing NC II
Electrical Installation and Maintenance NC III
Electrical Installation and Maintenance NC II
Computer Hardware System